Posted at 04-10-2018
From the November 2017 to the beginning of February this year, Margiz has dismantled an autoclaved aerated concrete factory in Latvia, near Riga. The disassembly was performed for the Client from Africa, in order to rebuild it in Rwanda. After few months, the rebuilding plans has been detailed prepared ...
Posted at 01-02-2018
Our works in Saulkalne, Latvia, are soon to be completed. After two months of everyday hard work of our team, AAC Plant is almost empty, only few elements left to be dismantled. Last containers are being packed before the trip to Africa, and the dismantling areas are in cleaning process. Of course, we ...
Posted at 14-01-2018
When the AAC Plant was running, Silos were the place to store the lime powder and cement - raw materials for production. To dismantle those six huge silos we had to use 200 tones crane. With this kind of helper, dismantling went easy and fast.
Posted at 12-01-2018
After the Christmas and New Year's break, from more than a week, further disassembly works have been carried out at the project site in Latvia. The last two weeks of disassembly left. The outer parts of the autoclave are already cut into smaller pieces and loaded into containers. Below are some photos ...
Posted at 11-12-2017
Works in Latvia are in full swing. Our team is working on dismantling the machine turning the semi-product, and the cross-cutter, being part of the aerated autoclaved concrete production line. Below are some photos from ongoing works:
Posted at 01-12-2017
Time to unveil the secret - from the beginning of November we are working on a new project. This time, work are in Latvia and we are performing a complete disassembly of the autoclaved aerated concrete production line. Our matchmarking team has been working intensively for over the last two weeks, this ...